Marty Burger Named Co-CEO of Silverstein Properties
December 13, 2011
New York City developer Larry A. Silverstein today announced the appointment of Martin S. Burger as Co-Chief Executive Officer of Silverstein Properties, Inc. The appointment is an extension of the Read more...

WTC Construction Update, November 2008

LowerManhattan.info

 

The following lists the major work taking place currently at the site:

Freedom Tower:

Installation of tower-foundation steel columns (two cranes on site)

·                       Installation of tower-foundation steel columns (two cranes on site); superstructure reached grade in July 2008

·                       Pouring concrete for the foundation and rebar installation for core and sheer wall

·                       Utility installation and tie-ins

 

WTC East Bathtub:

·                       Excavation of the Tower Two site through October 2008; crews are working double shifts

·                       Concrete pours began at the Tower 4 site in July 2008

·                       Major excavation of the south half of the east bathtub (sites of Towers Three and Four) from July 2007 through February 17, 2008; Silverstein Properties's construction team is mobilized and preliminary construction is underway

·                       Structural support and excavation under the 1 train box, which runs through the WTC site along Greenwich Street

National September 11th Memorial and Museum:

·                       Slurry wall reinforcement

·                       The "Survivors Stairway" will be relocated to its permanent home in the underground Memorial by late 2008

·                       Steel installation began September 1, 2008

·                       Concrete installation begins in early 2009

·                       Memorial crews plan to remove the ramp into the WTC site by December 2008 to continue construction on the south footprint

·                       The World Trade Center Memorial Foundation announced on April 9, 2008 that it reached its $350 million private fundraising goal

 

Tower 4

·                       Excavation

·                       Foundation work including concrete pours

Tower 3

  • Excavation; rock blasting through fall 2008
  • Foundation work

130 Liberty Street/Deutsche Bank Building Deconstruction:

·                       Abatement crews are currently working downward

·                       Full decontamination is underway as of May 2008

Air-quality testing at the building continues, with 12 sampling sites in the building’s immediate vicinity. Air monitoring reports are available here; more information about air monitoring is available here and on the LMDC’s website.

Source: LowerManhattan.info