The World Trade Center site is by a long way the most extraordinary construction site anywhere in the world. The film Rebuilding the World Trade Center is documenting and bearing witness to the Read more...

WTC Construction Update, May 2009

Freedom Tower:

  • Steel installation (two cranes on site)
  • The south core is more than 140 feet above grade and rising
  • The north core is above grade as of late February 2009
  • Final concrete pours are taking place on the sub-grade structure
  • Utility installation and tie-ins
  • WTC East Bathtub:

  • Excavation of the Tower 2 site completed in April 2009; PA turnover to SPI pending
  • Structural support and excavation under the 1 train box, which runs through the WTC site along Greenwich Street
  • SPI's construction team mobilized at the Tower 4 site in early 2008
  • WTC Transportation Hub being demolished/excavated
  • National September 11th Memorial & Museum:

  • Slurry wall reinforcement
  • Steel installation at the site of both memorial pools began in September 2008
  • Cranes are mobilized on site as of December 2008
  • Concrete installation began in March 2009
  • Memorial crews removed the ramp into the WTC site in January 2009
  • The "Survivors Stairway" was relocated to its permanent home in the underground Memorial in December 2008
  • Tower 4:

  • Foundation work including steel and concrete installation; substructure to grade in late summer 2009
  • Port Authority turned over "offset" area near 1 train box; SPI now completing foundations
  • Paving for Vehicular Security Center ramp on southeast corner
  • Tower crane was installed in early March 2009; second crane to be installed in August 2009
  • Overnight utility work is active on Liberty Street for T4 tie-ins
  • Tower 3:

  • Excavation, rock blasting currently on hold
  • Foundation/infrastructure work underway for Cortlandt Way
  • Tower 2:

  • The Port Authority's offiical T2 turnover to Silverstein is pending