Marty Burger Named Co-CEO of Silverstein Properties
December 13, 2011
New York City developer Larry A. Silverstein today announced the appointment of Martin S. Burger as Co-Chief Executive Officer of Silverstein Properties, Inc. The appointment is an extension of the Read more...

WTC Construction Update, July 2009

Tower 1 (Freedom Tower):

  • Steel installation (two cranes on site)
  • Both the south and north cores is rising above grade
  • Final concrete pours are taking place on the sub-grade structure, including foundations for surrounding plaza
  • Utility installation and tie-ins
  • Crews are coordinating substructure construction while maintaining PATH service

East Bathtub:

  • Excavation of the Tower 2 site completed in April 2009; PA turnover to SPI pending
  • Structural support and excavation under the 1 train box, which runs through the WTC site along Greenwich Street
  • SPI's construction team mobilized at the Tower 4 site in early 2008
  • WTC Transportation Hub being demolished/excavated, including former H&M terminal

National September 11th Memorial & Museum:

  • Excavation of the Tower 2 site completed in April 2009; PA turnover to SPI pending
  • Structural support and excavation under the 1 train box, which runs through the WTC site along Greenwich Street
  • SPI's construction team mobilized at the Tower 4 site in early 2008
  • WTC Transportation Hub being demolished/excavated, including former H&M terminal

Tower 4:

  • Foundation work including steel and concrete installation; substructure to grade by early September 2009
  • Tower crane was installed in early March 2009; second crane to be installed in August 2009
  • Vehicular Security Center construction in tower substructure

Tower 3:

  • Foundation/infrastructure work underway for Cortlandt Way
  • The Port Authority's site turnover to Silverstein Properties is pending

Tower 2:

  • The Port Authority's offiical T2 turnover to Silverstein is pending