Construction Update, June 2011

 Memorial and Museum

  • More than 160 trees now on site
  • Finishing work on memorial reflecting pools and waterfalls, including bronze nameplate installation
  • Utilities, waterproofing, and other activities underway
  • Permanent stairways are being built
  • 1 World Trade Center
  • Facade installation is now above floor 38
  • Tower steel is now above floor 70
  • Concrete is now being installed

2 World Trade Center

  • Slab on Grade complete
  • B3-B4 core walls complete
  • B2  Slab 50% framed
  • Below grade MEP coordination on going 

 3World Trade Center 

  • Slab on grade complete. Core walls from B4-B3 in progress.
  • B3 slab formwork in progress.  
  • Tower Crane #2 to be installed the week of 6/20 
  • Below grade MEP coordination on going

 4 World Trade Center

  • Steel up to the 37th floor
  • Concrete poured up to the  32nd  floor
  • Core walls erected to  20th Floor 
  • Below-grade mechanical work currently underway as well as above-grade floors
  • Concrete "Creeper" crane to be attached to the building and operational by 6/25
  • Fireproofing operation on 12th Floor 
  • Elevator shaft work begun in Banks A, B & C
  • Curtain wall work has started partially on the 5th floor.