On this, the eighth anniversary of the Sept. 11 attacks, there is plenty of progress to be seen at the World Trade Center site.
The steel skeleton that will support the National Sept. 11 Memorial
& Museum is nearing completion. Excavation for the state-of-the-art
underground vehicle security center is underway on Liberty Street. One
World Trade Center, the largest of the four massive planned office
towers, rises more than 100 feet above street level, and a second tower
follows closely behind.
Still, the fully realized renewal of those 16 acres in the heart of Lower Manhattan remains very much in question.
A collapsed credit market, blown construction deadlines and opposing
assessments of Lower Manhattan's commercial strength have conspired to
put the site's owner, the Port Authority of New York and New Jersey, at
seemingly irreconcilable odds with its largest leaseholder, developer
Larry Silverstein. Even the state's three most powerful politicians-the
governor, the speaker of the Assembly, and the New York City
mayor-tried and failed to break the deadlock.
"That we are where we are after this much time," Speaker Sheldon
Silver said, "is an embarrassment to our city, our state and the
nation."
How did we get to where we are? The Trib looks back at a nearly year-long stalemate that, at this writing, knows no end.
SEEDS OF CONFLICT
In a most public mea culpa, the Port Authority admitted in June 2008
that its projects at the site were years late and billions of dollars
over budget. Among them are the 1,776-foot-tall 1 World Trade Center,
the iconic PATH transit hub, a complex infrastructure of utilities and
tunnels, and extensions of Greenwich and Fulton Streets that will
crisscross the site. The agency also admitted that it could not turn
over construction-ready land to Silverstein for his three planned
office towers along Church Street by its June 30, 2008, deadline.
Just as the Port Authority released new project deadlines in October,
the credit market collapsed. Suddenly unable to secure construction
loans for his towers, Silverstein claimed that were it not for the
Authority's delays, he would already have the money in hand.
"The Port Authority has not made good on its promises under the 2006
agreements," Silverstein wrote in a July letter to all involved in the
rebuilding. "If not for the Port's failures, the project would clearly
be much, much further along, and we would have had the opportunity to
finance in a much more positive economic climate."
In his letter, Silverstein said he planned to seek arbitration
against the Port Authority for the delays if a financing agreement for
the towers couldn't be reached. Port Authority executive director
Christopher Ward responded by saying he believed the Authority was in
the right, and it was "unfortunate" that Silverstein had chosen to
"walk away from the negotiating table."
"As the 2006 [agreement] makes clear, the Port Authority is meeting
all of its obligations, and we look forward to a quick arbitration
decision should Mr. Silverstein continue down this legal path," Ward
said.
Silverstein did just that, and last month filed for an arbitration
hearing against the Authority. He will argue that the Port Authority
violated the terms of the two entities' 2006 development agreement by
falling behind on its infrastructure projects. That same agreement
imposes a five-year time limit on Silverstein to build and open all
three of his towers, or he loses them to the Port Authority. The
five-year countdown began ticking on Aug. 24, when the Authority
finally turned over the last of the three sites for Silverstein's
towers.
A draft report by the Lower Manhattan Construction Command Center,
which became public last month, supported Silverstein's claims that the
infrastructure work is lagging. Port Authority officials insist that
the projects are on schedule.
"The dates are wrong," a Port Authority spokesman said. "Our
comprehensive analysis, completed every month, shows we are on schedule
to meet the completion dates we released last October."
WORTH THE RISK?
In addition to the issue of missed deadlines, another disagreement between
Silverstein and the Authority stands in the way of progress.
With credit unavailable in the private market, Silverstein and the Port
Authority have been locked in a months-long spat over financing for the
developer's towers. The Authority has repeatedly refused Silverstein's demands
that they guarantee construction loans for at least two of his towers. The
Authority said it would not guarantee loans without significant private sector
investments.
In his latest offer, Silverstein promised the Authority one third ownership in the towers if he
could tell private lenders that they had first priority when the time came to
repay the loans, but the Authority has insisted that it come first in line when
the loans come due.
"The market is telling us that [the towers] shouldn't rise, that there isn't a
market for these two buildings," Ward said during a City Council hearing last
month.
Exposing the Authority's portfolio of other transportation projects in the
region to "any increased risk," he said, would be irresponsible. "To build into
a market that private capital will not enter means that you are effectively
building socialized office space."
Janno Lieber, Silverstein's senior executive in charge of World Trade
Center construction, said
during the same hearing that the company "wasn't looking for a handout," and
blasted the Authority for rejecting the proposal.
"We're looking for a partnership," Lieber said. "They say that they want us to
raise money in the [private credit] markets. This is the one way that can be
done, and they've rejected it."